30 kilometers, of which 15.5 kilometers run underground.
Home›The Leader›Dubai Metro Blue Line Nears 30 Percent
The Leader · Dubai
The Dh20.5 billion Blue Line of the Dubai Metro is nearly 30 percent complete, and the design of its new train was unveiled on Sunday, November 22, 2026, when His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, reviewed progress at Dubai Festival City.
At a glance
Among the projects of the Dubai 2040 Urban Master Plan, few will change the daily life of residents and visitors as directly as the Metro's Blue Line. On Sunday, His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, visited the works at Dubai Festival City, where he reviewed progress on the Dh20.5 billion line and saw the design of the new train that will run on it. The project is now nearly 30 percent complete.
The figures behind that percentage are considerable. Some 14,000 workers, engineers and supervisors have recorded 33 million working hours on the line, and tunneling has been under way since May, when His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Ruler of Dubai, inaugurated it.
30 kilometers, of which 15.5 kilometers run underground.
Fourteen new stations, with interchanges to the existing Red and Green lines.
Mirdif, Dubai Silicon Oasis, Dubai Creek Harbour and Dubai International City, among others.
Scheduled for September 9, 2029, twenty years to the day after the Dubai Metro first opened.
The Roads and Transport Authority briefed His Highness on its use of artificial intelligence in railway inspection and maintenance, and on a research center with CASCO Signal that will house the Middle East's first train systems development laboratory.
For travelers, the Blue Line's most interesting stop is likely to be Dubai Creek Harbour, the waterfront district facing the old city across the creek, which today is reached most easily by car. A direct Metro connection will put its promenades and restaurants within easy reach of the hotels of Downtown and Deira. When the line is complete, the Dubai Metro will run to 131 kilometers with 78 stations and 168 trains, linking the city's five great urban centers named in the master plan: Bur Dubai and Deira, Downtown and Business Bay, Dubai Silicon Oasis, Dubai Marina and JBR, and Expo City Dubai.
The Blue Line is the first of two new lines. In April, Dubai announced the Dh34 billion Gold Line, 42 kilometers underground through 15 districts, due on September 9, 2032. Our page on the Dubai D33 agenda and the 2040 Urban Master Plan explains how transport, housing and green space fit together, and our guide to the future of travel, from air taxis to high-speed rail follows the region's wider ambitions.
Until 2029, the Red and Green lines remain the visitor's most efficient way to cross the city at rush hour, and the cooler months from November to March are the pleasantest for combining the Metro with walks along the creek. Our UAE luxury vacations guide suggests where to stay, and our best time to visit the Middle East explains the seasons.
It is scheduled to open on September 9, 2029, the 20th anniversary of the Dubai Metro.